Inspection Projects

R&D Projects

 

Inspection Projects

Scope: Shore-pulling part of both phases on lay-barge
Total length of line in Phase 17: ~4.5 km
Total length of line in Phase 18: ~4.5 km
Line size (OD): 32 inches with a 4 inches Piggyback line
Welding method: Automatic welding
Inspection method: AUT (Automated Ultrasonic Testing)
Client: IOEC (Iranian Offshore Engineering and Construction)
Owner: POGC (Pars Oil and Gas Company)
Duration: 15 Days
Status: Finished
More...

Scope: Inspection of 1st stage Separator Vessels for Crack

Reference Standard: ASTM 577 & 578
Total number of vessels: 2
Material: A516 Gr.70 with Inconel cladding
Inspection methods: ToFD, Semi-mechanized PE, PE
Client:
Eni Iran BV
Duration: 20 Days
Status: Finished

Scope: Pipe-laying of both phases on lay-barge
Total length of line in Phase 17: ~102 km
Total length of line in Phase 18: ~109 km
Line size (OD): 32 inches with a 4 inches Piggyback line
Welding method: Automatic welding
Inspection method: AUT (Automated Ultrasonic Testing)
Client: IOEC (Iranian Offshore Engineering and Construction)
Owner: POGC (Pars Oil and Gas Company)
Duration: 5 Months
Status: Awarded-Pending

  • Sirri - Assaluyeh Pipeline Project

Scope: Pipe-laying on lay-barge
Total length of line: ~282 km
Line size (OD): 32 inches
Welding method: Automatic welding
Inspection method: AUT (Automated Ultrasonic Testing)
Client: IOEC (Iranian Offshore Engineering and Construction)

Owner:
Duration: 7 Months
Status: Finished

  • Inspection of Spherical legs

Scope: Detection and monitoring of corrosion under Fire Proof
No of tanks: 3
Legs per tank: 10
Inspection method: INCOTEST (Pulsed Eddy Current)
Client:
TORC (Tehran Oil Refining Co.)
Duration: 1 Month
Status: Finished

        Scope: Consultancy service on applicable NDT methods for the internal

                   inspection of crude oil pipelines
        Inspection method: NA
        Client:
OTC (Oil Terminals Company)
        Duration: 6 Months

        Status: Finished

        Scope: Inspection of several plant coated and buried pipings for the monitoring of

                   situation in Dorood, Foroozan and Aboozar plants- Kharg Island
        Inspection method: Guided Waves Ultrasonic

        Line sizes (OD): 4", 6", 8", 10", 12", 14", 16"
        Client:
PDF Group

        Owner: IOOC (Iranian Offshore Oil Co.)
        Duration: 10 Days

        Status: Finished

         Inspection of 4 Isomax reactors

Scope: Inspection of 4 Isomax reactors for HIC-HTHA and

          cracking/disbonding detection
Inspection method: AUBT, Phased Array, TOFD, Mapping,

                           Advanced UT techniques (velocity ratio), MPI

Material: A336 Gr. F21 with A321 Stainless Steel cladding

Thickness: 238mm Base metal+3.2mm Cladding

Client: Tabriz Oil Refining Co.
Duration: 15 days
Status: Finished

 

         South Pars Development phases 15&16

Scope: Pipe-laying of both phases on lay-barge
Total length of line in Phase 15: ~100 km
Total length of line in Phase 16: ~95 km
Line size (OD): 32 inches with a 4 inches Piggyback line
Welding method: Automatic welding
Inspection method: AUT (Automated Ultrasonic Testing)
Client:
IOEC/KITO (Iranian Offshore Engineering and Construction)
Owner:
POGC (Pars Oil and Gas Company)
Duration: 3 Months
Status: Phase 15, 76 Km finished
 

         Inspection of 3 Catalyst reactors

Scope: Inspection of 3 catalyst reactors
Inspection method: Phased Array, TOFD, MPI

Material: Carbon steel A 387 Gr.C FBQ

Thickness: 72, 73mm and 85mm

Client: Shiraz Oil Refining Co.
Duration: 7 days
Status: Finished

         South Pars Development Phase 12

Scope: Pipe-laying of both phases on lay-barge
Length of line in each Phase 12A,B,C: ~140 km
Total length: ~420 Km
Line size (OD): 32 inches with a 4 inches Piggyback line
Welding method: Automatic welding
Inspection method: AUT (Automated Ultrasonic Testing)
Client:
IOEC/KITO (Iranian Offshore Engineering and Construction)
Owner:
POGC (Pars Oil and Gas Company)
Duration: TBA
Status: One line completed, other lines in progress

 

R&D Projects